Along the busiest tourist streets in the centre of Scotland's historic capital looms a giant structure of metal poles and platforms.
For five years, Radisson's G&V Hotel on the corner of a key historic street and the adjacent bridge has been a covered eyesore.
Tourists find no available accommodations, foot traffic are directed through confined passages, and businesses have left the building.
Restoration efforts started in 2020 and was originally estimated to last a brief duration, but now fed-up residents have been told the structure could persist until 2027.
Sir Robert McAlpine (SRM), the primary firm, says it will be "close to the conclusion" of 2026 before the initial parts of the frame can be taken down.
Edinburgh's council leader Jane Meagher has labeled it a "eyesore" on the area, while heritage campaigners say the work is "very troublesome".
What is transpiring with this notoriously protracted project?
The establishment with 136 rooms was developed on the site of the previous regional authority offices in 2009.
Projections from when it first opened under the Missoni Hotel banner, put the build cost at about a significant sum.
Construction activity got underway not long after the start of the coronavirus outbreak with the hotel itself shut for business since 2022.
Part of the road and a large section of footpath leading up to the corner of the historic street have been left out of action by the development.
Pedestrians going to and from the Lawnmarket and Victoria Terrace have been compelled one after another into a narrow, covered walkway.
Seafood restaurant Ondine departed from the building and moved to St Andrews in Fife in 2024.
In a comment, its management said building work had forced them to modify the restaurant's look, adding that "patrons merited more".
It is also hosts restaurant chain Pizza Express – which has hung large signs on the framework to inform customers it is open for business.
An report to the a local authority committee in the start of the year indicated that the process of "revealing" the façade would start in February, with a total takedown by the end of the year.
But the contractor has said that is not the case, pointing to "highly complicated" construction issues for the delay.
"We expect starting to remove parts of the scaffold towards the end of next year, with subsequent enhancements proceeding afterwards," the company commented.
"We are working closely with the relevant stakeholders to ensure we deliver an enhanced site for the local area."
A heritage director, lead of conservation group the an advocacy group, said the work had added to the city's reputation of being "protracted" for construction projects.
She said those associated with the project had a "public duty" to minimise disturbance and should incorporate the work into the city's design.
She said: "It causes the experience for those on foot in that area of the city really difficult.
"It is puzzling why there is not some attempt to integrate it into the streetscape or produce something more creative and avant-garde."
A project spokesperson said work on "solutions to enhance the appearance the site" was ongoing.
They stated: "We acknowledge the frustrations felt by the community and shops.
"This has been a lengthy and protracted process, demonstrating the complexity and magnitude of the remedial work required, however we are committed to finishing this essential work as soon as is possible."
The council leader said the local authority would "maintain pressure" on those responsible to complete the project.
She said: "This structure has been a negative presence for years, and I understand the exasperation of locals and area enterprises over these persistent hold-ups.
"That said, I also recognize that the company has a obligation to make the building structurally sound and that this repair has proved to be hugely complex."
A seasoned casino enthusiast and gaming analyst with over a decade of experience in reviewing online casinos and slot games.